RUVUBU
BURUNDI
KEY FIGURES
MISSIONS REALISED BY DAMS AND GRIDS
  • Drone topographic survey with ground control points and terrain modelling
  • Geological assessment of the Kaburantwa river site
  • Hydrological study: 346 km2 catchment, flow-duration curve and design floods
  • Conceptual design: diversion weir, headrace canal, penstocks and powerhouse
  • Grid connection and transmission line design
​​CLIENT: SPV Kabu23 Hydropower

LOCATION

  • Installed capacity

  • Type of plant

  • Rated Discharge

  • Net Head

  • Production forecast

  • Current stage

16,5 MW

Run-of-river plant

11,3 m3/s

157,2 m

90,1 GWh

Feasibility completed