top of page
NJUMBI
KENYA
KEY FIGURES
MISSIONS REALISED BY DAMS AND GRIDS
  • Final Design Study (APD)
  • Acquisition of required licenses and authorizations following the local procedures
  • Environmental and Social Impact Assessment (ESIA)
​
CLIENT: Njumbi Hydro Power​
​

LOCATION

  • Installed capacity

  • Type of plant

  • Rated Discharge

  • Net Head

  • Production forecast

  • Current stage

8,5 MW

Hydropower plant

6,45 m3/s

166 m

41,7 GWh

Under development

image.png
7990c5d8-6963-4392-b73e-243f8988f772.png
bottom of page